6-11
31. A machine center can produce 175 units per day at 100% utilization. Demand is 75 units
per day, and suppliers are capable of delivering raw materials to support production of 125
units per day. If demand doubles, the flow rate will be
32. Which of the following statements is NOT correct?
33. The operations manager for Dogs R Us is trying to understand the bottleneck in the dog
grooming process. Times below are given in minutes per dog, and when there are two or more
employees they can process two or more dogs simultaneously.
Process step Time Who
Verify customer information 5 min./dog Front desk (staffed by 2 employees)
Crate the dog 2 Front desk
Wash and dry the dog 20 Washers (3 employees)
Nails and teeth 13 Nail/teeth specialists (2 employees)
Grooming 25 Groomers (4 employees)
Call customer for pick–up 5 Front desk
Assuming that demand and supply exceed capacity, what is the maximum flow rate (in dogs
per hour) for this process?