Chapter 15 – Materials Requirements Planning and ERP
16-10
28. Using a lot-for-lot ordering strategy for the following item, what is the net requirements
amount in week 3? (Note: Use a lead time of one week and the gross requirements and
scheduled receipts depicted below, and assume you begin with 100 units in inventory.)
Week 1 2 3 4
Gross requirements 0 100 80 15
Scheduled receipts 75 0 0 0
Projected ending inventory (100)
Net requirements
Planned order receipts
Planned order releases
29. Using a lot-for-lot ordering strategy for the following item, what is the planned order
release amount in week 3? (Note: Use a lead time of one week and the gross requirements and
scheduled receipts depicted below, and assume you begin with 50 units in inventory.)
Week 1 2 3 4
Gross requirements 0 100 80 15
Scheduled receipts 25 0 0 0
Projected ending inventory (50)
Net requirements
Planned order receipts
Planned order releases