19. In MRP “scheduled receipts” are
20. The master production schedule for Product A shows a need for 30 units, and Product B
shows a need of 25 units. To manufacture a unit of Product A, three units of component C are
required. To manufacture a unit of Product B, four units of component C are required.
Determine the gross requirements for component C to complete production.
21. End item A requires three component parts: B, C, and D. The bill of materials indicates
that for each completed A, one unit of B, 2 units of C, and 1 unit of D are required. Current
inventory for the four items is as follows: there are 18 As, 40 Bs, 50 Cs and 35 Ds in stock. If
the lead time for all items is one week and there are no scheduled receipts for any item, how
many units of product A can be delivered to customers at the start of next week (week 2)?