ANALYSIS OF THE PROBLEM
FOR THE USE OF ARBITRATORS
Twenty Seventh Annual Willem C. Vis
International Commercial Arbitration Moot
Vienna, Austria
October 2019 – April 2020
Oral Hearings
April 4 – 9, 2020
Organised by:
Association for the Organisation and Promotion of the
Willem C. Vis International Commercial Arbitration Moot
and
Seventeenth Annual Willem C. Vis (East)
International Commercial Arbitration Moot
Hong Kong
Oral Arguments
March 23 – 29, 2020
Organised by:
Vis East Moot Foundation Limited
© Association for the Organisation and Promotion of the Willem C. Vis International Commercial Arbitration Moot 2
Prof. Dr. Stefan Kröll
ANALYSIS OF THE PROBLEM
FOR USE OF THE ARBITRATORS
If you do not already have a copy of the Problem, it is available on the Vis Moot web
site, https://vismoot.pace.edu/site/27th-vis-moot/the-problem. If you downloaded the
Problem during October you will need to download the revised version issued at the
beginning of November which includes Procedural Order No 2 (PO 2) and subsequent
comments.
This analysis of the Problem is primarily designed for the use of arbitrators. Arbitrators
who may be associated with a team in the Moot are strongly urged not to communicate
any of the ideas contained in this analysis to their teams before the submission of the
Memorandum for Respondent.
The analysis will be sent to all teams after all Memoranda for Respondent have been
submitted. Many of the team coaches/professors participate as arbitrators in the Moot
and therefore receive this analysis. It only seems fair that all teams should have the
analysis of the Problem for the oral arguments. If the analysis contains ideas teams
had not thought of before, the respective teams will still have to turn those ideas into
convincing arguments to support the position they are taking. At the same time, the
analysis is not intended to give away all possible arguments. For that reason, this
analysis often does no more than merely flag the issue without mentioning the
arguments for or against a certain position. It does not contain a full analysis of the
problem.
All arbitrators should be aware that the legal analysis contained herein may not be the
only way the Problem can be analyzed. It may not even be the best way that one or
more of the issues can be analyzed. The number of issues that arise out of the fact
situation makes it necessary for the teams to decide which of the issues they
emphasize in their submissions and oral presentations. Arbitrators should keep in mind
that the team’s background might influence its approach to the Problem and its
analysis. In addition, the decision may be influenced by the presentation a team has
to respond to. Full credit should be given to those teams that present different, though
fully appropriate, arguments and emphasize different issues.
In the oral hearings, in particular in the later rounds, arbitrators may inform the teams
which issues they should primarily focus on in their presentation, if they want to discuss
certain issues specifically. They should do so, if they want to make the in-depth
discussion of a particular issue part of their evaluation.
© Association for the Organisation and Promotion of the Willem C. Vis International Commercial Arbitration Moot 3
Prof. Dr. Stefan Kröll
THE FACTS
I. The Parties and Contractual History
CLAIMANT, HydroEN plc, is a market leader in providing pump hydro power plants. It
operates in over 100 countries and has an annual turnover of US$ 4.3 billion and has
more than 25,000 employees. It is well known to realise pump hydro power plants in
challenging environments conforming to the highest environmental protection
standards.
RESPONDENT, TurbinaEnergia Ltd, is a world-renowned producer of premium water
turbines. It produces its turbines with 400 employees in Equatoriana and 150
employees in Danubia and has an annual turnover of US$ 180 million.
RESPONDENT’s premium product is the R-27V Francis Turbine with a capacity of 300
MW. It has been presented to the general public in 2013 and has at the time been the
most expensive turbine in the market. One of the particular features of the R-27V
Francis Turbine following from its design and the materials used is an increased
corrosion and cavitation resistance which allows for longer inspection and
maintenance intervals (Respondent Exhibit R 1). For the short inspections, the
intervals could be extended from 2 to 3 years and from 12 to 13 years for the interim
inspection while a main inspection should be done every 26 years.
The dispute arose out of a Sales Agreement, concluded on 22 May 2014, in which
CLAIMANT purchased two R-27V Francis Turbines for its Greenacre Pump Hydro
Power Project.
Greenacre is a city of 100,000 people situated among the rolling hills of Western
Mediterraneo, a remote part of Mediterraneo. Due to the Terranean mountain range,
the region is separated from the rest of the country and only connected to the energy
grid of the neighbouring country Ruritania.
For the last ten years Greenacre has moved towards being a sustainable community,
including adopting a Sustainability Bill of Rights. In 2010 the Council of Greenacre, with
the support of 82% of the population, adopted a “no-carbon” energy-strategy. It
provided for a massive increase of the wind and solar energy production capacity to
an extent that the energy generated this way would generally meet the demand. A
cornerstone in that strategy was the construction of a pump hydro power plant. Its
primary purpose was to make the availability of renewable energy largely independent
from the weather conditions which affect the production of wind and solar energy. In
times of overproduction the excess energy produced by the wind turbines and the solar
panel is used to pump the water from the lower reservoir into the upper reservoir. From
there, the water is then released again to the lower reservoir powering the turbines
whenever the demand exceeds the supply of green energy produced by the wind parks
and the solar panels. By being able to use a considerable amount of excess energy at
times of overproduction and to release energy promptly when needed, the power plant
also plays an important role in stabilizing the local Greenacre energy grid.
© Association for the Organisation and Promotion of the Willem C. Vis International Commercial Arbitration Moot 4
Prof. Dr. Stefan Kröll
On 15 July 2014, CLAIMANT was awarded the contract for the construction and
operation of the pump hydro power plant as the result of a public tender process which
the Council of Greenacre had initiated in January 2014. In preparation of its bid
CLAIMANT had contacted RESPONDENT already in March 2014 to enquire about a
potential delivery of two R-27V Francis Turbines to be included into the plant should
the contract be awarded to CLAIMANT (Claimant Exhibit C 1). RESPONDENT was
very willing to do so and both Parties signed a Sales Agreement on 22 May 2014,
according to which RESPONDENT was to deliver and install two R-27V Francis
Turbines should CLAIMANT be awarded the tendered contract (Claimant Exhibit C 2).
The inclusion of RESPONDENT’s newly developed, innovative, and powerful R-27V
Francis Turbine were an important factor for the success of CLAIMANT’s bid. First,
they allowed for a more environmental-friendly design of the plant since only two
turbines were needed to guarantee the needed power of 600 MW. Second, they also
should have allowed for longer inspection and maintenance intervals. This was an
important consideration since generally each inspection and maintenance results in a
reduced availability of the plant of approximately 4-6 weeks. The inspection of each
turbine takes around 2-3 weeks, during which only the other turbine is available to
manage the supply of energy. Furthermore, for the inspection works at the generator
and the penstock the whole plant has to shut down. Thus, during the inspection time,
the plant is, at best, only 50% available to store the surplus of energy at peak
production times and to release it at times when the demand exceeds the energy
produced by the other renewable energy sources. As a consequence, such energy
needed would have to come from one of the only two other sources available, i.e. two
stacks of powerful batteries of 50 MW each and the coal fired power plant close to the
border in the neighboring Ruritania, which is the only conventional power plant
connected to the Greenacre grid.
The local authorities in Greenacre made it clear during the tender process that one of
the relevant considerations for the selection of the contractor was to avoid or at least
minimise the need to rely on such carbon-based energy. That was already mentioned
in the preamble of the model contract contained in the tender documentation which the
successful bidder had to conclude with the Council of Greenacre. The councilor in
charge of the project, Mr. Gilbert Crewdson, subsequently even insisted on an
amendment of the contract to include an express commitment by CLAIMANT to
guarantee the availability of the plant for at least eleven months per year for the
production of at least 600 MW. Thus, the contract between the Council of Greenacre
and CLAIMANT now contains a penalty of US$ 40,000.00 for each day in which the
non-availability of the pump hydro power plant makes it necessary to rely on “dirty
energy” from Ruritania to meet an excess of demand which could not be fulfilled by
solar or wind energy (Claimant Exhibit C 6).
To exclude as far as possible the need to buy any energy from the coal fired plant in
Ruritania, CLAIMANT had planned to schedule all necessary inspections during the
vacation time in September/October. In normal years, during the vacation time of eight
weeks, the other sources of renewable energy could be expected to produce sufficient
energy to meet the reduced demand. There are very few hours during night- time when
the demand is likely to exceed the energy produced. In these few hours the two battery
stacks should generally be sufficient to provide the required additional quantity of
energy. Consequently, if the inspections can be done as planned in
September/October, it is very likely that despite the non-availability of the pump hydro
power station an actual purchase of energy from the coal fired power plant in Ruritania
could be avoided. The latter would only provide reserve energy capacity to guarantee
a supply in case of unforeseen events or extreme whether situations. There was,
however, the clear expectation that there would be no need to use such reserve
capacity.
Unfortunately, July/August and November/December are the months of peak demand
and a high volatility of the energy produced by wind turbines and solar panels. During
these four months the pump hydro power plant is operating largely at “full speed” due
to the extremely volatile production rates of the other sources of renewables. Any
standstill of the hydro power plant or a reduction in production during these four months
will definitively result in the need to purchase missing energy from the only further
available source of energy connected to the grid in Greenacre, the existing old coal
fired power plant in Ruritania. Also, in the remaining months, the energy produced by
the power plant is generally required to meet the demand so that in a case of a standstill
of the plant it would have to be replaced by energy from the coal fired plant in Ruritania.
After winning the contract on 15 July 2014, CLAIMANT immediately started with the
construction of the pump hydro power plant and managed to finalise it in less than
four years. In late spring 2018, RESPONDENT delivered and installed the two R-27V