CHAPTER 8
1. The authors recommend preparing a schedule for each __________.
a) work package in the WBS
b) task in the WBS
c) major task level in the WBS*
d) project that has a WBS
Response: Refer to the section: Background
2. In application, PERT(ADM) has primarily been used for __________.
a) construction projects
b) manufacturing projects
c) industrial projects
d) research and development projects*
Response: Refer to the section: Network Techniques: PERT (ADM) and CPM (PDM)
3. The critical activities in real-world projects typically constitute less than __________% of the total activities in the project.
a) 5
b) 10 *
c) 30
d) 50
Response: Refer to the section: Network Techniques: PERT (ADM) and CPM (PDM)
4. Which of the following is NOT a software tool, commonly used to manage projects, especially in relation to time and cost
budgets?
a) Microsoft Project
b) Microsoft Excel
c) Crystal Ball
d) Microsoft Word*
Response: Refer to the section: Using These Tools
5. In the AOA network, circles depict ________.
a) networks
b) events*
c) logical dependencies
d) dummy activities
Response: Refer to the section: Network Techniques: PERT (ADM) and CPM (PDM)
6. Most commercially available project management software applications use the __________.
a) GERT chart
b) Bar chart
c) AOA network
d) AON network*
Response: Refer to the section: Network Techniques: PERT (ADM) and CPM (PDM)
7. The calculation of the standard deviation for the beta distribution is based on the assumption that __________.
a) the range is divided by a count of the values used to compute the mean
b) the range is approximately equal to six times the standard deviation*
c) the standard deviation is 50 percent of the mean
d) the standard deviation is the square of the statistical variance
Response: Refer to the section: Network Techniques: PERT (ADM) and CPM (PDM)
8. Task F has duration of 10 days and an earliest start date of 20 days. Based on the given data, determine the early finish
duration for task F.
a) 10 days