Project Management l CHAPTER 13
13.49 Slack time in a network is the
(a) time consuming job or task that is a key subpart of the total project.
(b) shortest amount of time that could be required to complete the activity.
(c) amount of time that you would expect it would take to complete the activity.
(d) amount of time that an activity can be delayed without delaying the entire project.
(e) none of the above
ANSWER: d
13.50 A network activity is a
(a) point in time that marks the beginning or ending of an activity.
(b) time consuming job that is a subpart of the total project.
(c) graphical display of a project.
(d) network technique that allows three time estimates for each activity in a project.
(e) the longest time path through the network.
ANSWER: b
13.51 Which of the following is not a concept associated with CPM?
(a) normal time
(b) probability
(c) normal cost
(d) crash cost
(e) deterministic network
ANSWER: b
13.52 PERT
(a) assumes we do not know ahead of time what activities must be completed.
(b) allows computation of the program’s evaluation.
(c) is a network technique that uses three time estimates for each activity in a project.
(d) is a deterministic network technique that allows for project crashing.
(e) none of the above
ANSWER: c
13.53 CPM
(a) assumes we do not know ahead of time what activities must be completed.
(b) is opposite to that of PERT, as it does not consider the network activities.
(c) is a network technique that allows three time estimates for each activity in a project.
(d) is a deterministic network technique that allows for project crashing.
(e) none of the above
ANSWER: d
13.54 Managers use the network analysis of PERT and CPM to help them
(a) derive flexibility by identifying noncritical activities.
153