Problem Set 4 Roy Hendro Baskoro Widjanarko 18/423483/EK/21807
2. a. r1= 11%, r2= 10%, r3= 9%, r4= 8%, Cost = $10 Million, and Yield Payoff in 4 year = $15 Million
PV1 = FV / (1+r1)4
PV1 = $15 M / (1+0,11)4
PV1 = $15 M / 1,52
PV1 = $ 9.880.965
Jadi, kita jangan mengambil
proyek tsb sebab PV < Cost.
PV2 = FV / (1+r2)4
PV2 = $15 M / (1+0,10)4
PV2 = $15 M / 1,46
PV2 = $ 10.245.202
Jadi, kita sebaiknya mengambil
proyek tsb sebab PV > Cost.
PV2 = FV / (1+r3)4
PV3 = $15 M / (1+0,09)4
PV3 = $15 M / 1,41
PV3 = $ 10.626.378
PV4 = FV / (1+r4)4
PV4 = $15 M / (1+0,08)4
PV4 = $15 M / 1,36
PV4 = $ 11.025.448
PV = FV/(1+r)n