86
Solutions Manual for Berk/DeMarzo/Stangeland
•
Corporate Finance
, 4
th
Canadian Edition
Copyright © 2019 Pearson Canada Inc.
8-6.
Timeline:
0 1 2 3 6 7 16
–200,000 –200,000 –200,000 –200,000 300,000 300,000
a.
66 10
66 10
200,000 1 1 300,000 1
NPV = 1 + 1
rr
1r 1r 1r
200,000 1 1 300,000 1
=1+ 1
0.1 0.1
1.1 1.1 1.1
= $169,482.24
Since NPV > 0, the company should take the project.
b. Setting NPV = 0 and solving for r (using a spreadsheet), the answer is IRR = 12.66%. So, if the
estimate is lowered by more than 2.66%, the decision will change from accept to reject.
c.
66 10
66 10
200,000 1 1 300,000 1
NPV= 1 + 1
rr
1r 1r 1r
200,000 1 1 300,000 1
11
0.14 0.14
1.14 1.14 1.14
$64,815.87
Since NPV < 0, the company should not make the investment.
8-7.
a.
b. The IRR is the point at which the line crosses the
x
-axis. In this case, it falls very close to 13%. Using
Excel, the IRR is 12.724192%.