Question 1 – 87234
The two major types of risk affecting a firm are:
A) financial risk and cash flow risk.
B) business risk and financial risk.
C) business risk and collection risk.
The correct answer was B) business risk and financial risk.
Business risk is the uncertainty regarding the operating income of a company. Financial risk refers to
the uncertainty caused by the fixed cost associated with borrowed money.
Question 5 – 97597
A company is considering the purchase of a copier that costs $5,000. Assume a cost of capital of 10
percent and the following cash flow schedule:
Year 1: $3,000
Year 2: $2,000
Year 3: $2,000
Determine the project’s NPV and IRR.
NPV IRR
A) $883 20%
B) $243 20%
C) $883 15%
The correct answer was A) $883 20%
To determine the NPV, enter the following:
PV of $3,000 in year 1 = $2,727, PV of $2,000 in year 2 = $1,653, PV of $2,000 in year 3 = $1,503.
NPV = ($2,727 + $1,653 + $1,503) − $5,000 = 883.
You know the NPV is positive, so the IRR must be greater than 10%. You only have two choices, 15%
and 20%. Pick one and solve the NPV. If it is not close to zero, then you guessed wrong; select the
other one.
[3000 ÷ (1 + 0.2)1 + 2000 ÷ (1 + 0.2)2 + 2000 ÷ (1 + 0.2)3] − 5000 = 46 This result is closer to zero
(approximation) than the $436 result at 15%. Therefore, the approximate IRR is 20%.
Question 6 – 96775
Which of the following statements is least accurate regarding the marginal cost of capital’s role in
determining the net present value (NPV) of a project?
A) Projects for which the present value of the after-tax cash inflows is greater than the present
value of the after-tax cash outflows should be undertaken by the firm.
B) The NPVs of potential projects of above-average risk should be calculated using the
marginal cost of capital for the firm.
C)
When using a firm’s marginal cost of capital to evaluate a specific project, there is an implicit
assumption that the capital structure of the firm will remain at the target capital structure over
the life of the project.
B was correct!
calculate NPV -> WACC=MCC
The WACC is the appropriate discount rate for projects that have approximately the same level of risk
as the firm’s existing projects. This is because the component costs of capital used to calculate the
firm’s WACC are based on the existing level of firm risk. To evaluate a project with above (the firm’s)
average risk, a discount rate greater than the firm’s existing WACC should be used. Projects with