Armco, Inc.: Midwestern Steel Division
1. The old performance measurement system had the following problems:
– It did not provide information on the product mix being produced. It provided data on total
tonnage produced, but did not breakdown “what” was produced.
The system compared “actual” to “objective” but did not provide data on what factors caused
variance.
– Costs were not broken down by:
o Fixed costs
o Variable costs
o Relevant Range
– Reports were generated on the 15th day following each month end. Therefore, time lag would not
allow the managers to take immediate corrective actions.
– It did not measure Key Performance Index (KPIs’) for each department.
– The system did not highlight data that was outside the norm.
– Between 1985 1989, Melt Shop man-hours (MH) have been reduced by 20.4% but $/NT has
only reduced by 8.4%